University of Kansas: Memorial Union

For nearly a century, the University of Kansas Memorial Union has served as both a memorial to KU students and alumni lost in World War I and the heart of student life on campus. After decades of daily use, many areas were ready for a refresh. The goal was to create a brighter, more welcoming experience that respects the Union’s history, all while keeping the busy building open throughout construction.

Project Details

Renewing the Heart of the Kansas Union

DI began with strategic master planning for KU’s Memorial Union, helping establish a vision and prioritize improvements that could be phased over time. The fourth-floor lobby became the first step in that plan, with DI serving as prime experiential contractor to coordinate construction, finishes, building systems, accessibility updates, immersive technology and wayfinding while the Union remained fully operational. The refreshed space features an LED fireplace lounge, custom architectural woodwork, integrated digital displays and dimensional Jayhawk ceiling elements inspired by the original tile graphics. The result is a brighter, more welcoming campus experience that respects the Union’s historic legacy while better supporting students, visitors and daily campus life.

 

Challenge

The University of Kansas Memorial Union has served as a gathering place for nearly a century. Created as a memorial to KU students and alumni who died during World War I, the building remains both a meaningful campus landmark and an active space for student life. After decades of daily use, however, many areas were ready for a refresh, including the fourth-floor main lobby, where finishes had remained largely unchanged since the early 1990s.

Rather than approach the project as a single renovation, KU Memorial Union wanted to establish a broader vision for improving spaces throughout the building over time. The goals were to create a brighter, more welcoming experience, respect the Union’s history, prioritize improvements within available funding and keep the busy facility open throughout construction. As with any renovation of a historic building, the team also had to plan for unknown conditions, from uneven flooring to existing materials that could only be fully understood once demolition began.

 

SOLUTION

Dimensional Innovations began with strategic master planning for the Union, helping KU establish a cohesive design direction, identify priorities and determine how improvements could be phased over time. The fourth floor became the first step in that multiphase vision, giving the team an opportunity to introduce a fresh look and functionality that could help inform future renovations throughout the building.

Throughout design development, DI worked closely with KU Memorial Union to align the scope with available funding, evaluating design priorities, materials and construction requirements together rather than treating them as separate decisions. This collaborative approach helped the team focus investment where it would make the greatest impact while developing a realistic path from design through construction.

Serving as the prime experiential contractor for the first phase, DI coordinated selective demolition, construction, architectural finishes, building systems and accessibility requirements across the lobby, lounge, corridor, vestibule and Jayhawk Walk areas.

 

Impact

By completing the first phase while the building remained operational, DI helped KU minimize disruptions to daily campus life. The project also establishes a cohesive design direction for future improvements, giving KU a practical roadmap for updating the historic building over time as funding becomes available.

Flooring became one of the project’s largest scopes—and one of its most technically challenging. Once the existing finishes were removed, the team uncovered uneven travertine and sections of an old brick sidewalk, revealing that portions of the current interior had once been outside.

Both surfaces required extensive preparation and leveling before the new flooring could be installed. DI Build turned those difficult existing conditions into a bright, modern foundation that visually connects the lobby and supports the rest of the renovated environment.

A previously blank wall was transformed into an inviting lounge feature anchored by an LED fireplace and large custom mantel. Architectural woodwork, including floating shelves, walnut seating surfaces, slat walls and coordinating ceiling details, brings warmth and texture throughout the space.

Slide 1 of 3

Ceiling

When the original custom tile Jayhawks were removed from the floor, the familiar detail was displayed overhead through bright, dimensional Jayhawk ceiling elements. Visible from across the lobby, the new feature preserves the spirit of the former design.

Technology

Large digital displays were integrated into the architectural slat wall to support directories, maps, calendars, event information and other campus communications. Smaller graphic updates were also incorporated near Jayhawk Ink on the second floor.